A factory needs to produce 1,800 jars of peanut butter on a certain day.
They start production at 8:30 A.M. By 10:30 A.M., they have produced 600 jars of peanut butter.
At what time will they complete the total number of jars that they need to produce? I am very confuzed and state test is coming up I need help because I am stuck and can't afford to pay for one on one tutor on here
In two hours, they have produced 600 jars. so they are working at 300 jars per hour. 1800-600=1200 and 1200 divided by 300 is 4 so they will finish work at 10:30+4:00, 14:30/2:30pm